REGULAR MONTHLY MEETING – July 11, 2006
The Town Board of the Town of Cooperstown met on July 11, 2006 at
7:00 PM at the Town Hall for the regular monthly meeting. Meeting
called to order by Chairman Bill Enz at 7:00 p.m. Present other than
Chairman Enz were Supervisors John Hager, Joe Havlovitz, Mike Albers
and Fred Lemens, Treasurer Bernie Duescher and Clerk Sue Kornely.
Constable Nancy Weber was not present. Seven others in attendance.
Representative Michelle Strauss from Horton Group, Lawrence Hansen
from Maritime Insurance, Jeff Reesman from Northeast Asphalt & John
Delmore from Scott Construction were also present. Pledge of
Allegiance. Motion to approve agenda Sup. Lemens/Sup. Albers. Carried
5/0.
Minutes of June 13th- reviewed/motion to approve Sup. Albers/Sup.
Havlovitz. Carried 5/0.
Minutes of July 5 Board of Review- reviewed/motion Sup. Hager/Sup.
Lemens. Carried 3/0.
Minutes of July 5th- reviewed/motion to approve Sup. Albers/Sup.
Lemens. Carried 5/0.
Treasurer’s Report- reviewed/motion to approve Sup. Lemens/Sup.
Havlovitz. Carried 5/0.
Citizens Input- Pat Bradley would like the sidewalk to stay. He would
like Bonnie Reddy’s sidewalk to stay also and would maintain both. He
feels in removing them the speed of the cars would increase.
Discussion.
Road and Equipment Report/Culvert Permits- Dan Kasten is out and John
Rabenhorst is covering. No culvert permits, John is cutting back
trees, cleaning out under the guardrails. Crackfilling machine is
ready.
Constable Report- Clerk Kornely reported on the cat issue on
Fairhills Road
Plan Commission- Sup. Lemens reported on the Rezoning request for
Ileana Link Christl, discussed Windmills ordinances- more restrictions
or compensations for neighbors or Town, discussed possible changes in
PC with rotating after 6 yrs with one year off & Town Board member for
each cycle, next meeting Aug 7th @ 7pm
Building Inspector- Clerk Kornely reported inspections on Wake &
Roznik homes.
County Hwy R curb and gutter project/Waterline from Manitowoc to
Green Bay- Chairman Enz reported he spoke with Gary Kennedy on the
patching of Hwy R, litigation on the parts over the centerline areas,
by next year the road will be complete, Pat Bradley asked about the
curbing. Sup. Hager reports thin layers of blacktop this year. Sup.
Lemens has concern with *narrowing road makes the road less safe*. Pat
Bradley would like the town to pay some of the curbing cost if
removed. Sup. Albers reported on the Waterline- 80% complete, cable
4-6 week project, expected completion November 12th, December 12th -
flush pipe. Motion table Sup. Lemens/Sup. Albers. Carried 5/0.
SVRS Voting Systems-Motion to order M100 voting machine Sup.
Albers/Sup. Hager. 5/0 C.
Viking Rescue Squad Contract- Sup. Hager reported on the meeting at
the Denmark Village Hall everyone discussing contact, another meeting
end of month. Chairman Enz had Leroy Meles attend the meeting also.
They are working on the contract wording; bi-laws and contract are not
consistent. Motion table Sup. Lemens/Sup. Havlovitz 4/0 C. Sup Hager
abstained.
Rezoning Request Ileana Christel- Sup. Lemens reported on the PC
finding, request to rezone 9.7 of the 21.2 acres to A-2, was denied by
the Plan Commission, the rezoning did not meet the Comprehensive Plan
preserving prime ag land and keeping the open and rural landscape.
Motion for denial Sup. Lemens/Sup. Albers. 5/0 C. Letter to County.
Road Bids for 2006-
1 - Kvitek Road from Cooperstown Road to Zander Road --- 1.06 mile by
21 feet
132 ton spot cold mix wedging, 20% double seal with a full hot
oil seal coat
Scott Construction - washed chip $17943.00 pea stone $16173.00
2 - Zander Road from Kvitek Road to the bridge --- .91 mile by 20.5
feet
full hot oil seal coat with the southern half double sealed
Scott Construction - washed chip $12831.00 pea stone $10920.00
3 - Devil River Road south of Zander Road
fill and pave inside corner, 140 feet by 8 feet
cold mix wedge and seal low area, 160 feet by 18 feet
repair far cul-de-sac
Scott Construction - $4950.00
4 - Herold Road between Cooperstown Road and Zander Road
spot wedge and seal several areas - approx. 264 ton cold mix
Scott Construction- $14378.00
5 - Herold Road from Zander Road to Hickory Hills Road --- 1.00 mile
by 21.5 feet
full cold mix wedge and seal coat
Scott Construction - washed chip $41124.00 pea stone $39973.00
6 - Hidden Valley Road --- .50 mile by 22 feet
110 ton spot cold mix wedge and seal coat
Scott Construction - washed chip $9725.00 pea stone $9249.00
7 - Hostak Road between Pautz *Pantzlaff *Road and Greenstreet
Road
spot patch seal coat
Scott Construction - $1875.00
8 - Hidden Valley Road west of County R --- 300 feet by 22 feet
full cold mix wedge and seal coat
Scott Construction - $3141.00
9 - Schley Road between County T and Pleasant Road
spot patch seal coat
Scott Construction - $1875.00
10 - Entrance off of Pleasant Road --- triples seal coat gravel
surface
Scott Construction - $300.00
11 - Herold Road --- 1.00 mile of 2” hot or cold mix
with reclaim, fine grade and pave
Scott Construction - $54350.00
Manitowoc County - 64385.00
NEA - ˝ mile $33960.00 1 mile $65520.00
Fahrner Asphalt Sealers, Inc---Thank you- no bid.
John Delmore stated to receive TRIP money you have to take the lower
bid. Discussed bids, vote on all but #11, Motion to chip with *washed
chip* Sup. Albers/ Sup. Hager. 5/0 C. Motion to approve bid for 1-4 &
6-10 to Scott Construction Sup. Lemens/ Sup Hager. 5/0 C. NEA will
extend price until next month per Jeff Reesman. Motion table #11 until
next month with concern to the TRIP program requirements Sup.
Albers/Sup. Lemens. 5/0 C. Scott Construction to start tomorrow.
Insurance Bids-move to next on agenda, Michelle Strauss from Horton
Group, Lawrence Hansen from Maritime Insurance presented their quotes,
Motion to remain with Maritime Insurance with replacement insurance
Sup. Albers.Sup. Lemens.
Application for Permit to Perform work within Cty Hwy ROW- Motion
table Sup. Albers/Sup. Havlovitz. 5/0 C.
Application for Culverts- Motion table Sup. Albers/Sup. Havlovitz.
5/0 C.
Signing & Signing Quotes- Motion table Sup. Havlovitz/ Sup. Lemens.
5/0 C.
Operator Licenses- background checks okay Amy Smith- motion to
approve Sup. Albers/Sup. Hager 5/0 C, Jessie Rolfe- motion to approve
Sup. Lemens/ Sup. Havlovitz 5/0 C, Crystal Wakker- motion to approve
Sup. Hager/ Sup. Albers 5/0 C, Clarence Schneider- motion to approve
Sup. Hager/ Sup. Albers 5/0 C.
150th Town Anniversary- Sup. Hager is working on *and looking for
volunteers to help*. Table Sup. Havlovitz/ Sup. Lemens. 5/0 C.
Board of Review Date- set for 6:45 on August 8th before Town Board
Meeting
Emergency Government Management- discussed, motion table Sup. Hager/
Sup.Lemens 5/0 C.
Employee Compensation for Dan Kasten- $.50 wage increase with next
pay period, motion Sup. Havlovitz/Sup. Lemens. 5/0 C.
2006 Municipal Officials’ Event July 19th
Other Business- Kocian Road Bridge 6-4-07 with 8-15-07 completion
cost $95,441.93 local 20% 10% Cty refund following year. TRIP max
allowed $26,704.29
Bills - reviewed/motion Sup. Albers/Sup. Lemens 5/0 C.
Correspondence- reviewed
Next Month's Agenda Items- curb & gutter, waterline, Road Bids,
Application-culverts, Road Signing and Road Sign Quotes, 150th
Anniversary, Emergency Government, BOR
Adjournment- motion to adjourn Sup. Hager/Sup. Albers. 5/0 C. 10:02
p.m.
Minutes approved August 8, 2006 Submitted by Susan Kornely,
Clerk